An employee is enrolled in the following accrual plans, both of which are linked to the same absence type:
Floating Holiday - Priority 100 - (Balance = 2 days), no negative balance allowed.
Vacation - Priority 200 - (Balance = 3 days), negative balance allowed with a limit of 2 days
Describe how a 7-day absence will be processed using this absence plan setup.
A. Decrease Vacation balance by 3 days and Floating Holiday balance by 2 days.
B. Decrease Floating Holiday balance by 2 days and Vacation balance by 3 days.
C. Decrease Floating Holiday balance by 2 days and Vacation balance by 5 days.
D. Decrease Floating Holiday balance by 2 days and Vacation balance by 2 days.
E. Decrease Vacation balance by 5 days and Floating Holiday balance by 2 days.
A customer requires their administrator to enter the paternity leave for their employees. Paternity leave can only be entered if an employee hasn't taken an absence called special absence in the previous 30 days of the paternity leave start date. The customer requires also that this paternity leave absence is only available for the employees who have one year of seniority in the company. Employees should notify of the absence at least 30 days in advance of the start date of the absence; otherwise, the absence is not considered timely.
Which configuration should you use to implement these requirements?
A. 1) Create an absence type using a childbirth or placement pattern. 2) Enable administrative updates. 3) Create a validation formula with the logic to evaluate if the "special absence" was taken 30 days before this absence and add it to the absence type. 4) Create an eligibility profile with the criteria of employees with 1 or more seniority in the company and add it to the absence type. 5) Select the qualified entitlements check box and set the evaluation rule to check for 30 days from the start date.
B. 1) Create an absence type using a childbirth or placement pattern. 2) Enable administrative updates. 3) Create, a validation formula with the logic to evaluate if the "special absence" was taken 30 days before this absence and add it to the absence type. 4) Create an eligibility profile with the criteria of employees with 1 or more seniority in the company and add it to the absence type. 5) Configure the late notification evaluation rule according to the requirement of at least 30 days in advance of the start date.
C. 1) Create an absence type using a childbirth or placement pattern. 2) Enable administrative updates. 3) Create an eligibility profile with the criteria of employees with 1 or more seniority in the company and add it to the absence type. 4) Create an absence certification of type Documentation that prevents absence entry if linked absence of type Special absence exists in the previous 30 days.
D. 1) Create an absence type using a childbirth or placement pattern. 2) Enable administrative updates. 3) Create a validation formula with the logic to evaluate if the "special absence" was taken 30 days before this absence and add it to the absence type. 4) Create an eligibility profile with the criteria of employees with 1 or more seniority in the company and employees with "male" gender and add it to the absence type. 5) Configure the late notification evaluation rule according to the requirement of at least 30 days in advance of the start date.
Your customer has an absence type that is linked to an accrual plan and has "Deferred processing on initial entry" enabled.
Which ESS job will you run to ensure that the accrual plan entries are created for the absence?
A. Evaluate Absences
B. Update Accrual Plan Enrollments
C. Update Accrual Plan Entries
D. Calculate Accruals and Balances
E. Evaluate Certification Updates
A customer created a public holiday on the 25-Dec-2018 (Tuesday) and assigned it to a geography to which an employee belongs to. However, the employee does not have a work schedule assigned. The employee records an absence from 24-Dec-2018 (Monday) to 26-Dec-2018 (Wednesday) using an absence type that measures duration in Days.
What will be the duration of the absence recorded?
A. 2
B. 4
C. 3
D. Absence cannot be recorded without a work schedule.
E. 1
You want to implement public holidays and would like to avoid having to change the work schedule if a public holiday is added or changed.
How do you achieve this?
A. Create Calendar Events and assign them as exceptions within the work schedule.
B. Create Calendar Events with Public Holiday as category and assign that calendar event category as an exception within the work schedule.
C. Create Resource Exceptions and assign them within the schedule.
D. Create Calendar Events with Public Holiday as category and assign each of them as exceptions within the work schedule.
E. Create Calendar Events as Resource Exceptions and assign them within the work schedule.
You have a requirement to base the accrual definition on Legal employer seniority date. The accrual will be given based on the Legal employer seniority date and will be different for varied length of service.
Which configuration meets this requirement?
A. Define a Length of Service Derived Factor, link the Derived Factor definition to one or more rows of the Accrual Matrix on the Accrual page of an Accrual Plan.
B. Define a Length of Service Derived Factor, link the Derived Factor definition to an Eligibility Profile, link the Eligibility Profile to the Accrual page of an Accrual Plan.
C. Define a Length of Service Derived Factor, link the Derived Factor to the Plan Attributes page of an Accrual Plan.
D. Define a Length of Service Derived Factor, link the Derived Factor definition to an Eligibility Profile, link the Eligibility Profile to the Participation page of an Accrual Plan.
Your customer wants to track overdue certifications of a Business Unit in a specific Legislative Data Group.
As an absence administrator, how do you accomplish this?
A. Run the Evaluate Absences process with an effective date, BU, and LDG as parameters.
B. Run the Update Action Items process with an effective date, BU, and LDG as parameters.
C. Run the Evaluate Certification Updates process with an effective date, BU, and LDG as parameters.
D. Run the Reprocess Certifications process with an effective date, BU, and LDG as parameters.
How do you set up varied payment percentages for an absence period for workers, based on the length of service for a qualification absence plan?
A. Specify the payment percentages in the Qualification Band Matrix and Qualification Details.
B. Configure payroll formula to determine the payment percentage for the qualification band level.
C. Use eligibility profiles to control the payment percentage that workers are eligible to in a plan.
D. Payment percentages cannot vary between workers in the same plan.
Which are the different types of absence plans available?
A. Holiday Plan, Illness Plan, Qualification, No Entitlement
B. Agreement Plan, Accrual Plan, Qualification Plan, Donation Plan, Compensatory and No Entitlement Plan
C. Accrual Plan, Holiday Plan, Qualification Plan, Donation Plan, Compensatory and No Entitlement Plan
D. Holiday Plan, Sickness Plan, and Maternity Plan
E. Agreement Plan, Accrual Plan, Qualification Plan, Shared Leave, Compensatory and No Entitlement Plan
You created an absence plan that allows negative balance and set the carryover rule to Flat Amount = 5 days.
Employee X has 10 days of entitlement left at the end of the leave year. Employee Y has -5 days of entitlement left at the end of the leave year.
How much balance would employees X and Y carry over into the new leave year?
A. Y carries 0 days and X carries -5 days.
B. X carries 10 days and Y carries 0 days.
C. X carries 5 days and Y carries 5 days.
D. X carries 5 days and Y carries -5 days.
E. X carries 5 days and Y carries 0 days.