In a manufacturing plant, a production operator in a given shift completes a car assembly and reports this using orderless completion by referencing a Work Definition. Identify the two purposes of the referenced Work Definition in Orderless reporting.
A. Material usage
B. Resource usage
C. Processing steps
D. Scrap material
E. Return material
In a manufacturing plant, the work definition and rate plans of Material, Resource, and Overhead of an assembly have been defined as required. A cost accountant created different scenarios to represent different manufacturing and cost assumptions and compare the results. When the cost assumptions are finalized, the cost accountant is expected to publish the cost scenario to cost accounting. Identify three process steps that the cost accountant has to perform to transfer the assembly to cost accounting in frozen type.
A. Publish cost planning scenario to Accounting.
B. Build cost planning scenario and perform cost roll up.
C. Create Accounting Distributions.
D. Transfer transactions from production to Costing.
E. Define a cost planning scenario with Material, Resource, Overhead cost plans, and work definition.
F. Transfer Transactions from Inventory to Costing.
You can generate and manage work order exceptions in Oracle Manufacturing Cloud. Which users can report production exception and who gets notified after an exception is raised?
A. The Production Operator can report and exception and the application generates a notification that is
sent to all users who have access to the manufacturing plant.
B. The Production Operator can report an exception and the application generates a notification that is sent to all users with the role of production supervisor who have access to the manufacturing plant.
C. The Production Operator or Manufacturing Engineer can report an exception and notifies the production supervisor using Oracle Social Network since there is no system generated notification.
D. The Production Operator can report an exception and notifies the production supervisor using Oracle Social Network since there is no system-generated notification.
A manufacturing plant works for two shifts of 8 hours each. The Manufacturing user wants a work center resource R1 of 4 units to be available during a nonworking time outside the regular shift on a particular day. Identify the sequence of steps to create a resource exception in the Manage Work Center Resource Calendar page.
A. Click Outside the existing Shift time on a Specific Date> Create Work Center page> Click the Resource Availability tab> Click Add icon> Select R1 from Resource Drop-down list> Enter 4 in Default Units Availability column.
B. Click Inside the existing Shift time on a Specific Date> Action Menu> Select Create Resource exception> Populate Start and Duration Field> Resource Availability region> Populate 4 units in Default Availability column.
C. Click Inside the existing Shift time on a Specific Date>Create Work Center page>Click the Resource Availability tab>Click Add icon> Select R1 from Resource Drop-down list> Enter4 in Default Units Available.
D. Click Outside the existing Shift time on a Specific Date> Action Menu> Select Create Resource exception> Populate Start and Duration Field> Resource Availability and Overrides Region> Populate 4 units in Availability Override column.
Identify two conditions that should be met at the same time for a Standard Operation to be called an Optional Operation.
A. There are no components attached to it.
B. The Automatically Transact check box is deselected.
C. The Automatically Transact check box is selected.
D. The Count Point check is selected.
E. The Count Point check box is deselected.
Your Customer has implemented Oracle Cloud Manufacturing and the Manufacturing user is in the
process of defining Work Definition and Operations. However, this user is unable to assign an ad hoc item,
Grease, to an operation.
Identify the reason.
A. The user doesn't have Override Item Structure Components in the Work Definition privileges.
B. An item cannot be assigned on an ad hoc basis.
C. The user doesn't have access to the PIM module.
D. The user doesn't have Data access to create item structure.
You want to use a predefined Standard Operation in a Work Definition, but you also want to change the usage of the Standard Operation resource. Identify the setup required.
A. Deselect the Referenced check box while adding the standard operation to the work definition and change the usage manually.
B. Select the Referenced check box while adding the standard operation to the work definition and change the usage manually.
C. Use the Transfer and Edit Standard Operation functionality to edit the resource usage.
D. Use a Resource exception for the resource and alter its usage.
Your customer runs two daily shifts in her plant: Morning Shift and Evening Shift. A resource LATHE is assigned to the work center W1. There are five units of LATHE available, of which three units are available for the Morning Shift and the remaining units are available for the Evening Shits. Which two actions must you perform to associate LATHE with W1?
A. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 3 against the resource LATHE in the Morning Shift column.
B. Select the Available 24 Hours check box and in the Resource Availability region, enter 3 against the resource LATHE in the Morning Shift column.
C. Select the Available 24 Hours check box and in the Resource Availability region, enter 2 against the resource LATHE in the Evening Shift column.
D. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 2 against the resource LATHE in the Evening Shift column.
E. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 60% against the resource LATHE in the Morning Shift column.
F. Do not select the Available 24 Hours check box and in the Resource Availability region, enter 40% against the resource LATHE in the Evening Shift column.
Identify three types of Item Quantities displayed in the Work Order History tab.
A. Scrapped Quantity
B. In Process Quantity
C. Remaining Quantity
D. Total Quantity
E. Completed Quantity
Identify the three changes that are allowed to be made to active Work Definition in a Work Center, without creating a new version.
A. Delete an Operation
B. Costing Priority
C. Production Priority
D. Add an Operation
E. Completion Subinventory