An administrator wants to make sure that time remaining on work items in a plan view are consistent with
the estimate.
Which plan check ensures this?
A. Invalid Estimate Check
B. Planning Problems Check
C. Traditional Planning Check
D. Cross-Project Planning Problems Check
A user has a project with many build definitions and wants them to be easy to find. How can these be organized?
A. Create tags and apply to appropriate build definitions.
B. Create labels and apply to appropriate build definitions.
C. Create folders and move appropriate build definitions into the folders.
D. Create collections and add appropriate build definitions into the collections.
A developer working in the RTC Eclipse client has checked in their changes and found that another
developer's incoming change set has affected the same file. The developer attempted to Auto Resolve the
conflict, but was unsuccessful.
Which of the following would cause this to occur?
A. The incoming change set appended new lines to the file.
B. The developer's change set included changes to multiple files.
C. Both change sets contained changes to the same line in the file.
D. Work items related to the change sets affect the same component.
Management is asking for report describing all RTC users, team areas, team members and corresponding
process roles, as well as team area administrators for an RTC project area.
How should the report be created?
A. Generate Runtime Report using the RTC Eclipse client.
B. Use the "repotools-jts" utility with the "exportUsers" option.
C. Export users from the Team Organization View in the RTC Eclipse client.
D. Export the users from the "Active Users" menu on the JTS Application Administration Web Page.
A scrum master needs to manage work items from multiple project areas and create a cross-project plan
with a set of master work items. The scrum master wants to see a roll up of the schedules of work items
related to the master work items.
Which work item link type permits this?
A. Parent
B. Tracks
C. Resolves
D. Depends On
A development team is utilizing a project area built on the scrum template. The scrum master wants to understand how much estimated work remains in the iteration and projection for completion. What action would the scrum master take to assess this?
A. Examine the Ranked List of work items.
B. View the Burndown Chart in the plan Details.
C. Compare the plan's Initial to Planned snapshot.
D. Review the Effective Estimate and Time Spent in the Roadmap.
An organization is considering utilizing preconditions to enforce process behavior of work items. Which elements define the configuration? (Choose three.)
A. Role
B. Release
C. Timeline
D. Work Item
E. Editor Presentation
F. Operation Behavior
A project manager determines the current iteration is complete and decides that the next iteration should
be started.
How is this done?
A. Set the current iteration's status to complete.
B. Set the next iteration as the current iteration.
C. Specify that a release is scheduled with the next iteration
D. The start and end dates will automatically start the next iteration.
A user wants a query to filter work items in the closed group of a workflow. Which option in the query condition allows this?
A. Resolved
B. Unassigned
C. Unresolved
D. Current Iteration
A scrum master wants to determine if the team has enough time to complete the work planned for an
iteration.
What is used to assess this?
A. Plan's Task Board View
B. Ranked List of work items
C. Load Bar in the Plan Details
D. Traceability View sorted by Estimate