What is a deliverable of the Application. Customer Team Enablement work stream in the Prepare phase of
SAP Activate?
Please choose the correct answer. Response:
A. Project Charter
B. Project Documentation
C. Knowledge transfer to end users
D. Learning plan
What is the final activity in the Realize phase of a new implementation of SAP S/4HANA cloud edition?
Please choose the correct answer.
Response:
A. Data migration
B. End-to-End walkthrough
C. Readiness check
D. Solution validation
What is the minimum number of quality gates mandated by the SAP Activate methodology? Please choose
the correct answer.
Response:
A. 0
B. 3
C. 4
D. 5
Response:
A. Manage roles of configuration users
B. Train new users
C. Create test data
D. Test configured processes
E. View solution scope
What is the focus of a SCRUM of SCRUMS in an Agile context? Please choose the correct answer.
Response:
A. Best Practice adoption
B. Communication to the Project Management Office
C. Backlog management
D. Integration topics
What are the three pillars of SAP Activate? There are 3 correct answers to this question. Response:
A. SAP Activate Methodology
B. SAP Best Practices
C. SAP S/4HANA in-memory database
D. SAP Solution Manager
E. Guided Configuration
Which deliverable is specific to on-premise and NOT for the cloud? Please choose the correct answer. Response:
A. Technical Design Solution
B. Knowledge Transfer
C. Adaptation Specification
D. Learning Needs Analysis
In which phase of the SAP Activate Methodology does the team complete the System Assessment?
Please choose the correct answer.
Response:
A. Deploy
B. Explore
C. Prepare
D. Realize
Who determines the tasks that are required to complete the committed backlog items in a sprint? Please
choose the correct answer.
Response:
A. Project Manager
B. Product Owner
C. Project Team
D. SCRUM Master
Which activities are part of the Application: Solution Adaption work stream of SAP Activate for new
implementations?
There are 3 correct answers to this question. Response:
A. Value Audits
B. Production Support Plan
C. Value Determination
D. Change Management Plan
E. Scope Validation