Which function allows you to check consistency of the dates within the project structure with or without
taking activities into account? Please choose the correct answer.
Response:
A. Sets of dates
B. Check dates
C. Planning methods
D. Extrapolate
How do you optimize cash flows to maximize project profits and reduce project costs? Please choose the
correct answer.
Response:
A. PS Cash management
B. Mile stone billing
C. Milestone management
D. Billing plan
Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships? Please choose the correct answer. Response:
A. Mass document function
B. Mass change function
C. Work function
D. Authorization function
Which of the following prerequisites need to be met in order to analyze the capacity requirements of an
activity? There are 3 correct answers to this question.
Response:
A. Scheduling must have been carried
B. A distribution key must be maintained in the work center
C. A work center must be maintained in the activity
D. The capacity requirements indicator must not be set in the network header
Which of the following aids in calculating actual overheads based on the costing sheet and overhead key
entered?
There are 3 correct answers to this question.
Response:
A. WBS element
B. Assignment
C. Network header
D. Network activity
Items procured through which of the following methods are not assigned to a stock segment and do not pass through a warehouse? Please choose the correct answer.
A. Directly
B. Non project stock items
C. Indirectly
D. Vendors
Which indicator determines whether summarization is executed on the basis of classification or master data characteristics; in a network profile? Please choose the correct answer.
A. Capacity requirement indicator
B. Version profile indicator
C. Proj.summ.master data indicator
D. Project summarization indicator
Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships? Please choose the correct answer.
A. IVIass document function
B. Authorization function
C. Work function
D. Mass change function
Assume you have information on sources of supply, quantities, and prices and you have decided to use
unit costing to produce a cost plan per WBS element.
Which of the following costs can be planned?
There are 3 correct answers to this question.
Response:
A. Cost element level
B. Each material
C. Each internal activity
D. Internal service
Response:
A. Plant order
B. Network order
C. Plant maintenance
D. Process order