Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
A. Network profile
B. Project profile
C. Parameters for the network type
D. Network type
You are using WBS elements and activities are NOT assigned. Which statements apply to the maintenance of the actual start and finish? Note: There are 2 correct answers to this question
A. You can only maintain the actual finish if all lower-level WBS elements have an actual finish date and the status of the WBS element is "Released"
B. You can always maintain the actual start if the WBS element has the status "Released" or "Partially released"
C. You can always maintain the actual start and finish date of a WBS element
D. You can only maintain the actual start of a WBS element if the finish date is not maintained
For which objects can billing plans be created? Note: There are 2 correct answers to this question
A. WBS elements
B. Project definition
C. Sales order items
D. Milestones
Which of the following factors influence the scheduling of internal processing activities? Note: There are 3 correct answers to this question
A. An activated Scheduling indicator in the control key of the internal processing activity
B. Whether the work for the internal activity is greater than its duration
C. The unit (for example, hour, day) of the field Normal Duration field of the activity
D. The relationships between activity elements
E. The factory calendar in the work center used for the internal processing activity
Project Structures
You are using assembly processing. You need to determine the delivery date of a sales order item with an account assignment to the project.
What are the prerequisites? Note: There are 3 correct answers to this question
A. A bill of material with sales views
B. A material master with sales views
C. Assignment between material and standard network
D. Standard network with activities
E. A production order
You have a project with a network, material and milestone. You want to plan an activity to start two days after its predecessor. How can you do that?
Note : there are 2 correct answers for this question.
A. Use an offset of two days for the relationship of both activities.
B. Use an offset of two days for milestone date.
C. Use an offset of two days for the requirement date of the material component
D. Calculate the start date of the activity and set the constraint "Must start on" accordingly.
Project Structure
Your customer has implemented budgeting for projects. The current budget of their projects has been changed several times. Therefore they want to get an overviews of the budget updates.
What standard report do you recommend?
A. Structure overviews for budget.
B. Cost element report on budget updates.
C. Line item report for budget
D. Hierarchical report on budget updates.
You want to create purchase requisition for the material used in your project. However after releasing the project, no purchase requisition has been created. What could be the reason?
Note : there are 2 correct answers for this question.
A. The procurement type in the material master is set to in-house Production.
B. The item category of the materials is set tstock item.
C. The material have no material number.
D. The item category of the materials is set tnon-stock item.
Which of the following is visible in the project planning board? Note: There are 2 correct answers to this question
A. Project-relevant purchase orders
B. Capacity requirements
C. Maintenance orders assigned to an activity
D. Production orders assigned to WBS elements
When you create a service activity in your network, what data can be entered? Note: There are 3 correct answers to this question.
A. Service specification
B. Overall limit (maximum value of all unplanned services)
C. Service purchase order number
D. Material master within service specification
E. Vendor