You want to use the different options for planning in SAP ECC. What is the correct sequence of the planning procedures?
A. Sales and operations planning -> Demand management -> Long-term planning -> Material requirements planning -> Capacity planning
B. Demand management -> Sales and operations planning -> Capacity planning -> Long- term planning > Material requirements planning
C. Material requirements planning -> Demand management -> Sales and operations planning -> Longterm planning -> Capacity planning
D. Long-term planning -> Sales and operations planning -> Demand management -> Material requirements planning -> Capacity planning
Which data forms the basis for calculating the capacity requirement for an operation? (Choose three.)
A. Standard values (routing)
B. In-house production time (material master)
C. Transport time (routing)
D. Formulas (work center)
E. Operation control key (routing)
Which of the following features are offered by MRP areas in SAP ECC? (Choose two)
A. A storage location may be assigned to different MRP areas.
B. An MRP area may include different storage locations.
C. Make-to-order production is supported by storage location MRP areas.
D. Subcontracting is supported by MRP areas.
The company you advise wants to carry out the material availability check automatically in the production order at various points in time. Which of the following options would you recommend? (Choose two.)
A. Goods receipt for the product produced with the order
B. Creation of the production order
C. Confirmation of the operation that the materials being checked are assigned to
D. Release of the production order
E. Goods receipt for a missing part
From what point can you no longer use the Read PP master data in the production order?
A. After printing the order papers.
B. After the first posting of goods movements or confirmation.
C. From the release of the production order.
D. After assigning the confirmed quantity of a material component due to carrying out a material availability check.
Which of the following activities is necessary for the capacity availability check that can be carried out automatically when a production order is released?
A. Set the finite scheduling indicator and assign a checking rule in the work center for the operation to be checked.
B. Activate the availability check and assign an overall profile in the checking control of the order type / plant combination.
C. Assign an appropriate availability checking rule to the material master for the product.
D. Activate the availability check and assign an overall profile in the production scheduling profile.
What do you have to consider regarding lot size procedures?
A. The procurement quantity of a lot size procedure can be specified using a safety time period profile.
B. If a long-term lot size is used, procurement is conducted with a long-term perspective.
C. The lot size quantity can be influenced using a minimum lot size and the rounding profile.
D. If a make-to-order production strategy is used, only the lot-for-lot (exact) lot size can be applied.
Which of the following functions are available in SAP ECC when using capacity leveling? (Choose three)
A. Batch size optimization
B. Midpoint scheduling
C. Lot size optimization
D. Finite capacity scheduling
E. Setup time reduction
The final assembly of a finished product should only be triggered when a customer order arrives.
Which planning strategy for the finished product do you use?
A. Planning with make-to-stock (strategy 10)
B. Planning at the assembly level (strategy 70)
C. Planning without final assembly (strategy 50)
D. Planning with final assembly (strategy 40)
Which of the following structural elements does a process order have? (Choose three.)
A. Item data
B. Parallel sequences
C. Relationships
D. Phases
E. Characteristic-based process instructions