Which of the following is not a Product Owner responsibility?
A. Running the daily scrum meeting
B. Team communication
C. Gathering requirements for Product Backlog items
D. Inspecting work at Sprint Review
According to Scrum, the amount of time for a team to plan Sprint activities is expressed in what unit of time?
A. Weeks
B. Days
C. Hours
D. Minutes
You are the Scrum Master and your Development Team of 6 members has completed six Sprints with the following information:
Sprint 1: 10 pontos Sprint 2: 11 pontos Sprint 3: 15 pontos Sprint 4: 14 pontos Sprint 5: 15 pontos Sprint 6: 10 pontos
The remaining story points for product development total 42. What is the approximate number of Sprint required to complete product development?
A. 6
B. 5
C. 4
D. 3
Which of the following is not reflected in a Sprint Burn down Chart?
A. Total Days in Sprint
B. Number of Tasks Remaining
C. Day of Sprint
D. Work Hours Remaining
What artifact shows actual versus planned progress?
A. Work Flow
B. Burn down Chart
C. Task Breakdown
D. Stakeholders
On a new Scrum Team, the Development Team tell the Scrum Master that they don't feel the need for retrospectives. Which answer is correct?
A. Discuss with product owner
B. Start doing retrospectives
C. None of above
Who is ultimate responsible for the Product Backlog item estimates?
A. The Development Team
B. Scrum Master
C. Stakeholders
D. Project Owner
What is the maximum time that Scrum recommends the team spend in the daily scrum (daily standup)?
A. Fifteen minutes
B. Thirty minutes
C. One hour
D. Four hours
E. As long as it takes
True or False: Story Points are for sizing, not for time estimation?
A. True
B. False
Which of the following are the two features of the Scrum Teams? (Choose two.)
A. Rules of Etiquette
B. Cross-functional
C. Process Oriented
D. Can have multiple Product Owner's