Which is a purpose of the Risk theme?
A. Establish a procedure to ensure every change is agreed by the relevant authority before it takes place
B. Establish a cost-effective procedure to identify, assess and control uncertainty
C. Establish mechanisms to control any unacceptable deviations from plan
D. Establish mechanisms to manage risks at the corporate or programme level of an organization
Which is part of the PRINCE2 definition of a project?
A. An undertaking that consists of at least two management stages
B. A description of what must be delivered in order to gain acceptance
C. The total of a plan's products
D. A temporary organization that is created for the purpose of delivering business products
Which is a type of issue?
A. A lesson
B. A request for change
C. An Exception Report
D. A risk with an estimated high impact
Which product identifies the management stages and timescales of a project?
A. Project Brief
B. Project Product Description
C. Project Plan
D. Initiation Stage Plan
What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?
A. Directing a Project
B. Controlling a Stage
C. Managing a Stage Boundary
D. Managing Product Delivery
Which principle helps to define what should be included and what should be excluded from a project?
A. Defined roles and responsibilities
B. Focus on products
C. Manage by stages
D. Continued business justification
What product defines the reporting requirements between the Project Manager and Team Manager?
A. Project Brief
B. Product Description
C. Team Plan
D. Work Package
What product should be used to confirm the version number of ail products in a particular stage?
A. Issue Register
B. Product Status Account
C. Product Description
D. Configuration Item Record
Which is NOT undertaken during the Initiating a Project process?
A. Review why the project is needed
B. Identify if the project is sufficiently aligned with corporate objectives
C. Show how the outcome is to be achieved
D. Appoint an Executive and Project Manager
Which is a purpose of quality planning?
A. Define the structure of the project management team
B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
C. Document approval records for those project products that have met their quality criteria
D. Produce the Project Plan with resource and schedule information