You are the project manager of the NHQ Project. You have created the project network diagram as shown in the figure:
You are concerned about a risk on Activity G that if it happens will delay the project by four days. You would like to utilize float for Activity G. How much float is available for Activity G to help offset the risk event?
A. Five days
B. Four days
C. Eleven days
D. Zero
Ben is the project manager of the NHF Project for his organization. Some delays early in the project have caused the project schedule to slip by nearly 15 percent. Management would like Ben to find a method to recoup the schedule slippage and to get the project back on track. Management is risk- adverse with this project. Which of the following methods should Ben avoid to recoup the project time?
A. Crashing
B. Fast tracking
C. Critical chain methodology
D. Adding lead time
Holly is the project manager for her organization. She is creating the activity list and would like to tag those activities that are comprised of discrete effort. What is discrete effort?
A. It is a term used to describe activities whose effort cannot be directly measured to the project objectives.
B. It is a term used to describe activities whose effort can be directly measured and linked to the project objectives.
C. It is a term used to describe activities that are supportive of the project work, but not linked to the project deliverables.
D. It is a term used to describe activities that are core project management processes, but not core project activities.
You work as a project manager for BlueWell Inc. According to you, which of the following is an output of the Sequence Activities process?
A. Project scope statement
B. Project schedule network diagram
C. Activity list
D. Organizational process assets
Kay is the project manager of the QUI Project. This project is done but is also considerably over budget. Kay has elected to crash the project in order to recoup schedule delays but this increased the project costs. What should Kay do with the information regarding the schedule delays and cost overruns?
A. Create an entry in the lessons learned documentation and explain her reasoning behind the corrective actions.
B. Create an exceptions report.
C. Create a variance report.
D. File the information as part of the project final report.
You work as a project manager for BlueWell Inc. You must communicate on a regular basis with all of your project stakeholders. In your project, you have 755 stakeholders. How many communication channels exist in the project?
A. 284,635
B. 570,025
C. 569,270
D. 755
You are the project manager for GGY Project. You are working with your project team to record the actual durations for the activities they have completed in the project schedule. Mary, one of your project team members, wants to know why you need to know how long it actually took the project team to complete their assignments as long as the project work is completed. Which of the following is the best response for Mary's query?
A. Actual durations need to be recorded to track process improvement.
B. Actual durations need to be recorded to create the schedule baseline.
C. Actual durations need to be recorded to measure the actual progress of the project.
D. Actual durations need to be recorded to perform quality control on the project management processes.
You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty- five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. Management is concerned that this project will be over budget upon completion. Management would like to create a report telling them how much more the project will need to complete. What value should you tell management?
A. $566,305
B. $787,504
C. $1,312,504
D. $733,456
You are the project manager for your organization. You have recently noted some risks associated with some of the activities in your project. These risks can have schedule and costs impacts on your project and you need to address the risks through qualitative and quantitative analysis to confirm the depth of possible impact. Where should you document the risk information concerning the activities in your project schedule?
A. Risk management plan
B. Schedule management plan
C. Risk register
D. Activity attributes
Adrian is the project manager for her project. This new project needs to identify all the stakeholders that will be affected by the project's outcome. How stakeholders are usually identified?
A. Stakeholders are usually identified through a stakeholder register.
B. Stakeholders are identified by the project team, project sponsor, and management.
C. Stakeholders are identified through the project customers.
D. Stakeholders are usually identified by interviewing identified stakeholders and expanding the list until all potential stakeholders are included.