Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,
A. Management strategies
B. Plan
C. Stakeholder interests
D. Time-driven controls
Which regular report provides the Project Board with a summary of stage status?
A. Communication Management Strategy
B. Project Brief
C. Highlight Report
D. Checkpoint Report
Which is an objective of the Managing Product Delivery process?
A. Sign-off completed Work Packages
B. Ensure the Business Case is kept under review
C. Report progress to the Project Board
D. Ensure that work on products is authorized and agreed with the team
How is a Benefits Review Plan used in the Closing a Project process?
A. Checked for inclusion of activities to confirm those benefits which cannot be measured until after project closure
B. To capture the baseline measures against which to assess benefits
C. To capture side-effects (beneficial or adverse) identified during post-project benefits reviews
D. To gain approval for the post-project activities and transfer responsibility to corporate or programme management
Which is NOT a recommended quality review team role?
A. Administrator
B. Chair
C. Producer
D. Reviewer
Identify the missing words in the following sentence.
The Team Manager should check the [ ? ] for any interfaces that must be maintained while developing products.
A. Project Product Description
B. Project Plan
C. Checkpoint Report
D. Work Package
Which role does NOT set tolerances?
A. Corporate or programme management
B. Project Board
C. Change Authority
D. Project Manager
Which should be provided by corporate or programme management before the Starting up a Project process commences?
A. A Project Brief
B. Sufficient information to identify the prospective Executive
C. The Project Initiation Documentation
D. Authority to initiate a project
Which project characteristic suggests that projects should have a defined start and a defined end?
A. Change
B. Temporary
C. Cross-functional
D. Risk
Which process ensures that key roles and responsibilities are allocated before a decision is made to initiate a project?
A. Managing Product Delivery
B. Initiating a Project
C. Managing a Stage Boundary
D. Starting up a Project